The Brief

Years of exposure to the marine environment had caused serious deterioration to these concrete beams and columns. Large areas of spalling concrete with steel reinforcement exposed and cracking was evident throughout the structure.

The Solution

Due to cost implications and budget restrictions, a long term plan was developed where 2 bays were renovated each year over a five year plan.

Removal of deteriorated concrete, cleaning and/or replacement of reinforcement steel bars and repairing or re-casting of concrete sections was carried out.

A380 Ware Barton & Telegraph Hill (Southbound)

Concrete Repairs and Cathodic Protection

Hurst Castle

Concrete Repairs works to Grade 1 & 2 Listed building.

Bretonside Viaduct, Plymouth

Ford Road, Brays Close, Tiverton & Westexe South, Crediton

Concrete Repairs and Non Slip Coatings to Balconys, Stairways and Walkways.