The Brief

During the external refurbishment of the Highbury Trust building, the main contractor found defective concrete to the sills and heads of the window surrounds and defective concrete to the decorative features.

The Solution

SWCR Ltd were called in to carry out an initial survey to identify the extent of concrete repairs required and following the main contractor’s decision, SWCR Ltd were then asked to carry out repairs using traditional concrete repair methods and finished to match existing profiles.