Huller House & Cheese Warehouse

Project: Huller House
Client: Generator Developments, Testing & Concrete Repairs
Main contractor: Dawnus Construction Ltd
Date: April 2015 - October 2015

The Brief

Huller House and Cheese Building are Grade 2 Listed building which have been left unused for a number of years and fallen into dis-repair. They are now being redeveloped into 55 warehouse apartments, commercial office space with Quayside walkway situated over the floating Harbour and canal.

Each floor level had areas in need of repairs, Beams, Soffits and Columns inside the building and window lintels outside have severe cracking, spalling and corroded reinforcements.

The Solution

High Pressure Power washing to clean down areas and help identify defects was carried out. Survey and testing followed by full traditional concrete repairs were carried out to all defective areas in preparation for new internal and external finishes.

East Street, Newquay

Concrete Repairs & Coatings

Reception Tank, South Petherton

Concrete Repairs

Somerset Fire Stations

Concrete Repairs

Plymouth Argyle, Plymouth

Concrete Repairs