INTRODUCTION
The project included the removal of existing paving slabs over the structure,partial removal of the existing
structural slabs, strengthening of the structure by constructing a new structural slab over the existing,
application of a waterproofing/surfacing membrane, removal of the paint protection system on the underside of
the structure, localised concrete repairs, application of specialist coating finishes to walls and soffits and
application of anti-carbonation coating to the underside of the structure and edge beams, application of new
paint system to the existing handrails.
South West Concrete Repairs Ltd were sub-contracted to carry out the concrete repairs, specialist cementitious
coating finishes to the walls, beams and soffits, application of anti-carbonation coatings. |