South West Concrete Repairs Logo

CONTRACT HISTORY

 

FALMOUTH PIER

Main Contractor:
Symons Construction

Project: Prince of Wales Pier, Falmouth

Client: Carrick District Council

Main Contractor: Symons Construction

Start Date: 4 February 2008

 

INTRODUCTION

The contract was for the concrete repairs to beams and columns of the pier which had deteriorated over the years. The works have been programmed over a number of years with 2 bays being completed each year. South West Concrete Repairs Ltd were sub-contracted by Symons Construction to carry out work on bays 8-10.

 

 

  Falmouth Pier
     
Falmouth Pier before repairs
View showing defective beams in the foreground
and shutters fitted for re-casting towards the rear
View showing beams prior to repair
View showing beams prior to repair
     

PRODUCTS

Structural Repairs:

BASF Emaco S88C   Mortar
BASF Emaco S103   Concrete
  View showing repaired section of beam
View showing repaired section of beam
     


Come here directly? Go to South West Concrete Repairs Home Page

South West Concrete Repairs Ltd., 24 Furneaux Road, Milehouse, Plymouth PL2 3ES
Tel: 01752 561300 Fax: 01752 605900